Anunțul 564575-2026 pentru Danemarca – Maşini, aparate, echipamente şi consumabile electrice; iluminat – 145 kV GIS substations for Ølstykke (ØLS) este publicat de Energinet Eltransmission A/S și este încadrat la codul CPV 31000000.
Sinteză HarveyAI
Harvey procesează documentele acestei licitații...
Prices must be stated in the attached Price List and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR When evaluating 'Price', the Contracting Authority will evaluate the total cost (for evaluation purpose), cf. the Price List cell G14 Recommended spare parts and voluntary options will not be part of the evaluation.
Award criterion name LOT
Price
Award criterion number LOT
30 | 60 | 5 | 5
Award criterion number weight LOT
per-exa | per-exa | per-exa | per-exa
Award criterion type LOT
price | quality | quality | quality
Contract conclusion date
2026-08-10Z
Contract duration end date LOT
2029-01-15Z
Contract duration start date LOT
2026-08-10Z
Contract identifier
145 kV GIS substations for Ølstykke (ØLS) - Hitachi Energy Denmark A/S
Contract nature
supplies | supplies
Contract nature main LOT
supplies
Contract nature main PROC
supplies
Contract tender id
TEN-0001
Result LOT identifier
LOT-0000
Result value CUR NOTICE
EUR
Result value NOTICE
4084300
Organizații și puncte de contact96
Organisation city addinfo LOT
Fredericia
Organisation city buyer
Fredericia
Organisation city financing
Fredericia
Organisation city paying
Fredericia
Organisation city reviewinfo LOT
Valby
Organisation city revieworg LOT
Viborg
Organisation city signatory
Fredericia
Organisation city ted esen
Oslo
Organisation city tenderer
Skovlunde
Alte informații publicate32
Competition termination PROC
true
Customization id
eforms-sdk-1.13
Description PROC
The Contracting Authority wants to purchase one 3 phase, 145 kV, 50 Hz, gas-insulated switchgear (GIS) Alternative gas, double busbar for substation Ølstykke (ØLS) and delivered on Energinet’s site, ready for operation. The GIS Switchgear will be installed in a new building - The supply consists of 2 line-feeder bays, 2 (two) transformer bays, 1 bus bar coupler bays, and 2 (two) metering bays.
The Contracting Authority wants to purchase one 3 phase, 145 kV, 50 Hz, gas-insulated switchgear (GIS) Alternative gas, double busbar for substation Ølstykke (ØLS) and delivered on Energinet’s site, ready for operation. The GIS Switchgear will be installed in a new building - The supply consists of 2 line-feeder bays, 2 (two) transformer bays, 1 bus bar coupler bays, and 2 (two) metering bays.
Electronic auction LOT
false
Eu fund LOT
no-eu-funds
Gpa LOT
true
Identifier LOT
LOT-0000
Internal identifier LOT
23/03591
Place performance street LOT
Roskildevej 34,
Title LOT
145 kV GIS substations for Ølstykke (ØLS)
Procedură și anunț11
Form type
result
Legal basis
32014L0025
Legal basis NOTICE
32014L0025
NOTICE identifier
c6bfbd7d-83d0-4d69-8749-f71ebeab3c09
NOTICE subtype
30
NOTICE title
Danemarca – Maşini, aparate, echipamente şi consumabile electrice; iluminat – 145 kV GIS substations for Ølstykke (ØLS)
NOTICE type
can-standard
NOTICE version
1
Procedure accelerated
false
Procedure identifier
f21d6477-7b00-47cb-a1af-51b258fe1ba8
Câștigători și oferte10
Tender ranked res
false
Winner city
Skovlunde
Winner country
DNK
Winner country sub
DK012
Winner email
[email eliminat]
Winner identifier
39856638
Winner name
Hitachi Energy Denmark A/S
Winner post code
2740
Winner selection status
selec-w
Winner size
large
Loc de executare9
Place of performance
DK013 | DNK | DK013 | DNK
Place of performance city LOT
Ølstykke
Place of performance city PROC
Ølstykke
Place of performance country LOT
DNK
Place of performance country PROC
DNK
Place of performance post code LOT
3650
Place of performance post code PROC
3650
Place of performance subdiv LOT
DK013
Place of performance subdiv PROC
Clasificare CPV5
Classification cpv
31000000 | 31000000
Main classification LOT
31000000
Main classification PROC
31000000
Main classification type LOT
cpv
Main classification type PROC
cpv
Acord-cadru și sistem dinamic2
Dps usage LOT
none
Framework agreement LOT
none
Valori2
Total value
4084300
Total value CUR
EUR
Căi de atac1
Review deadline description LOT
Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision. Other complaints must be filed with The Complaints Board for Public Procurement within: 1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date); 2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision. 3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Date de contact publicate în TED
28
Contactele sunt disponibile utilizatorilor autentificați.Autentifică-te
Textul integral publicat de TEDextinde
Health, Safety and Environment in Delivery
Cyber Security
For the evaluation of the sub-criteria the below should be enclosed: A solution description which in detail describes the proposed solution and demonstrates how and to which degree the specifications set out in: • Cyber security documentation requirements for components at Energinet stations doc. no 23/03591-26 are fulfilled. • Cyber security functional requirements for components at Energinet stations doc. no 23/03591-27 The Tenderer must in addition fill out “Template - Cyber security requirements for components at Energinet stations” doc. No. 23/03591-30. The tenderer should be thorough and precise when describing the solution, as any insecurities and discrepancies may affect the evaluation. Any deviations regarding Cyber security should be listed in the Clarification List in the spreadsheet marked “Cyber security” (doc. no. 23/03591-17). If the tenderer is offering a cloud-based solution the tenderer should include any deviations to the attached documents: • Functional Cyber security requirements for SaaS - Cloud based services doc. no 23/03591-28 • Non-functional Cyber security requirements for SaaS - Cloud based services doc. no 23/03591-29 Any deviations regarding (cloud-based) Cyber security should be listed in the Clarification List in the spreadsheet marked “Cyber security” (doc. no. 23/03591-17). The proposed deviations to the Cyber Security requirements in doc. no 23/03591-27, doc. no 23/03591-28 (only for cloud-based solutions) and doc. no 22/02125-29 (only for cloud-based solutions) should be explained in detail especially considering to which degree the solution fulfils the specifications and explanation as to why the deviation is made. Further, please note that the elements marked in yellow in: Functional Cyber security requirements for SaaS - Cloud based services doc. no 23/03591-28 are mandatory, cf. section 2.7.1 of the present Tender Conditions, and therefore are not included in the evaluation. The evaluation will be based on the submitted Cyber Security solution description in relation to scope and complexity and the extent to which the tenderer describes a project specific Cyber Security solution in accordance with the Contracting Authority’s specifications, cf. Cyber security documentation requirements for components at Energinet stations doc. No. 23/03591-26. Further the evaluation will be based on the extent to which the tenderer’s submitted solution complies with the Contracting Authority’s specifications: • Cyber security functional requirements for components at Energinet stations doc. no 23/03591-27 Cloud based services: • Functional Cyber security requirements for SaaS - Cloud based services doc. no 23/03591-28 (only for cloud-based solutions) • Non-functional Cyber security requirements for SaaS - Cloud based services doc. no 23/03591-29 (only for cloud-based solutions) All deviations will be included in the evaluation of the sub-criterion "Cyber Security”, and it is noted that any deviations may lead to a reduction to the score depending on the content, clarity, and consequence. A minimum score of 4 must be achieved, cf. sub-section 2.7.1. An overall evaluation will be made of the sub-criteria Cyber Security.
Prices must be stated in the attached Price List and the defined price elements must be completed herein. Prices must be stated exclusive of VAT but inclusive of all other expenses associated with the purchase. Prices must be stated in EUR When evaluating 'Price', the Contracting Authority will evaluate the total cost (for evaluation purpose), cf. the Price List cell G14 Recommended spare parts and voluntary options will not be part of the evaluation.
Konkurrence- og Forbrugerstyrelsen
Complaints regarding a candidate not being pre-qualified must be filed with The Complaints Board for Public Procurement within 20 calendar days starting the day after the contracting authority has sent notification to the candidates involved, provided that the notification includes a short account of the relevant reasons for the decision. Other complaints must be filed with The Complaints Board for Public Procurement within: 1. 45 calendar days after the contracting authority has published a contract award notice in the Official Journal of the European Union (with effect from the day following the publication date); 2. 30 calendar days starting the day after the contracting authority has informed the tenderers in question, that the contracting authority has entered into a contract based on a framework agreement through reopening of competition or a dynamic purchasing system, provided that the notification includes a short account of the relevant reasons for the decision. 3. 6 months starting the day after the contracting authority has sent notification to the candidates/tenderers involved that the contracting authority has entered into the framework agreement, provided that the notification included a short account of the relevant reasons for the decision.
Hitachi Energy Denmark A/S
145 kV GIS substations for Ølstykke (ØLS)
Klagenævnet for Udbud
Price
Technical solution
Energinet Eltransmission A/S
The tenderer should include a detailed HSE-setup and RAMS (Risk Assessment and Method Statements) specifically for the tendered assignment, including detailed descriptions of risk management, on-site supervision, inspections and audits, HSE-accident and incident case handling, assuring a proactive HSE-culture. It is expected that the HSE setup and RAMS will include: • Risk assessments for the scope of work. • Identification of the top 5 (five) HSE-risks and mitigation actions • Method statements • Organization on site to ensure efficient supervision • Description of planned inspections and audits • HSE-accident and incident case handling including identification, mitigation, and investigation • Interface management regarding HSE tasks • Description of accessibility to inspection and maintenance equipment necessary during operation Activities to ensure a proactive HSE-culture on the construction site The Contracting Authority will evaluate the proposed “Health, Safety and Environment in Delivery” based on the submitted HSE-set-up. It will be evaluated positively that the tenderer submits a proactive and detailed HSE-setup and RAMS for this specific assignment which - considering the complexity and scope - especially concerning: • How risk assessments for the scope of work (health and safety) are conducted to ensure that risks are eliminated rather than mitigated • Identification of the top 5 (five) HSE-risks for the scope of work and the mitigating actions. • Method statements which are relevant, safe to work by and show knowledge of the scope of work, especially considering working at heights, heavy loads and installation works. • How organization on site is structured to ensure efficient supervision. • How inspections and audits are planned considering the complexity and scope of the assignment. • How HSE-accident and incident case handling are conducted considering the complexity and scope of the assignment, including identification, mitigation and investigation. • Interface management towards subcontractors (if any) Management of competencies, including statutory training and foreign contractor’s management of recognition of qualification/training • How easily displays and dials regarding operational inspections and maintenance are reached without use of ladders and platforms • How contractor will work with implementing a proactive HSE-culture on the construction site An overall evaluation will be made of this sub-criterion.
For the evaluation of the sub-criteria the following should be enclosed: A technical solution description which in detail describes the proposed solution (including de-sign, components, processes, tools to be used etc.) and demonstrates how and to which degree the competitive specifications as set out in: Technical Specifications – Substation 145 kV GIS – Gas Insulated Switchgear doc. no 23/039591-1 and Data list – 145 kV GIS for substation ØLS doc. no 23/03591-2, are fulfilled. The tenderer should be thorough and precise when describing the technical solution, as any insecurities and discrepancies may affect the evaluation. Further, please note that the elements marked in yellow in: Technical Specifications – Substation 145 kV GIS – Gas Insulated Switchgear doc. no 23/03591-1 are mandatory, cf. section 3.7.1 of the present Tender Conditions, and therefore are not included in the evaluation. The evaluation will be based on the submitted technical solution description in relation to scope and complexity of the tendered assignment cf. Technical Specifications – Substation 145 kV GIS – Gas Insulated Switchgear doc. no 23/03591-1, Data list – 145 kV GIS for sub-station ØLS doc. no 23/03591-2. It will be evaluated positively to what extent the tenderer’s proposed solution is relevant detailed, project specific, ensures a high level of performance, sustainability, demonstrates a high level of ability to identify relevant activities and challenges and proposes appropriate and project specific methods, tools and processes for managing such. In this context, the elements listed below are of particular importance: • Maintenance (cf. section 4.3 Maintenance, Data list – 145 kV GIS for substation ØLS doc. no 23/03591-2) will be evaluated positive if tenderer can document low maintenance costs combined with short outage time and extended time between maintenance intervals. Furthermore, a solution that gives the Contracting Authority easy access, overview and operation during daily operation will be evaluated positively. • Project specific description which provides information and procedure for; the Factory Acceptance Test (cf. section 7.2 Testing), Site Acceptance Test (cf. section 7.2 Testing), Technical data (Data list – 145 kV GIS for substation ØLS doc. no 23/03591-2) and documentation according to section 9.1 Documentation in Technical Specifications – Substation 145 kV GIS – Gas Insulated Switchgear doc. no 23/03591-1 provided with the tender, especially concerning: o General arrangement drawing o Single line diagram o Gas schematic diagram o List of special tools or fixtures required for installation, testing, maintaining and operating the equipment o Environmental guide for handling and decommissioning of Gas Insulated Switchgear media o Estimated time schedule for engineering, installation and commissioning cf. “Time and Payment schedule” doc. no. 23/03591-10. A minimum score of 4 must be achieved, cf. sub-section 3.7.1. An overall evaluation will be made of the sub-criteria Technical solution.
The Contracting Authority wants to purchase one 3 phase, 145 kV, 50 Hz, gas-insulated switchgear (GIS) Alternative gas, double busbar for substation Ølstykke (ØLS) and delivered on Energinet’s site, ready for operation. The GIS Switchgear will be installed in a new building - The supply consists of 2 line-feeder bays, 2 (two) transformer bays, 1 bus bar coupler bays, and 2 (two) metering bays.
Mercell Holding ASA
DNK
Carl Jacobsen Vej 35
01
Askekroken 11
[email eliminat]
none
Fredericia
145 kV GIS substations for Ølstykke (ØLS) - Hitachi Energy Denmark A/S
[telefon eliminat]
[telefon eliminat]/03591
supplies
price
8800
Tonne Kjærsvej 65
4084300
Viborg
large
3650
DK041
CON-[telefon eliminat]+02:00
[telefon eliminat]
quality
0
4731149
32014L0025
per-exa
2
5
can-standard
39856638
2000-01-01Z
https://naevneneshus.dk/start-din-klage/klagenaevnet-for-udbud/
37795526
DK032
TEN-0001
eforms-sdk-1.13
31000000
RES-0001
Nævnenes Hus, Toldboden 2
39314878
2026-08-12+00:00
30
complainants
980921565
electricity
[email eliminat]
[email eliminat]
02 ••• ••• 11+00:00
ted-esen
7[telefon eliminat]
[telefon eliminat]:02:20+00:00
[email eliminat]
selec-w
DK011
neg-w-call
DK013
DK012
Procurement - B
2500
2740
Ølstykke
ORG-0003
ORG-0004
ORG-0005
pub-undert
ORG-0001
ORG-0002
f21d6477-7b00-47cb-a1af-51b258fe1ba8
Oslo
EUR
[telefon eliminat]
NO081
Roskildevej 34,
2029-01-15Z
no-eu-funds
NOR
https://eu.eu-supply.com/ctm/company/companyinformation/index/228008
true
60
https://eu.eu-supply.com/ctm/supplier/publictenders?B=ENERGINET
ENG
eSender
no
156/2026
http://mercell.com/
LOT-0000
TPA-[telefon eliminat]Z
http://www.kfst.dk
[telefon eliminat]
[telefon eliminat]
Skovlunde
false
13:36:50+00:00
[email eliminat]
Valby
c6bfbd7d-83d0-4d69-8749-f71ebeab3c09
tenders
Meterbuen 33
Loturi TED
1
23/03591
145 kV GIS substations for Ølstykke (ØLS)
The Contracting Authority wants to purchase one 3 phase, 145 kV, 50 Hz, gas-insulated switchgear (GIS) Alternative gas, double busbar for substation Ølstykke (ØLS) and delivered on Energinet’s site, ready for operation. The GIS Switchgear will be installed in a new building - The supply consists of 2 line-feeder bays, 2 (two) transformer bays, 1 bus bar coupler bays, and 2 (two) metering bays.
31000000 — Masini, aparate, echipamente si consumabile electrice; iluminat
Rezultate și atribuiri TED
LOT-00004.084.300,00 EUR
Câștigător: Hitachi Energy Denmark A/S · CUI 39856638
Contract 145 kV GIS substations for Ølstykke (ØLS) - Hitachi Energy Denmark A/S10 aug. 20262 oferte primite
Detalii licitație
Descriere
The Contracting Authority wants to purchase one 3 phase, 145 kV, 50 Hz, gas-insulated switchgear (GIS) Alternative gas, double busbar for substation Ølstykke (ØLS) and delivered on Energinet’s site, ready for operation. The GIS Switchgear will be installed in a new building - The supply consists of 2 line-feeder bays, 2 (two) transformer bays, 1 bus bar coupler bays, and 2 (two) metering bays.